Project History

  • Idea initiated during 2002-03 under PM package for Tharparker development.
  • PC-1 Submitted during Dec. 2004.
  • Project approved on 25th November 2006.
  • Administrative Approval issued on 30th July 2008.
  • Initial Location was at Jamshoro, shifted to SBA on 30th March 2009.
  • Project Initial approved Cost Rs. 200.33 million

—  93.73   million Capital Cost

—  106.60 million Revenue Cost

  • Completion Period 36 Months (Three Years) From July 2008 to June 2011.
  • Revised PC-1 of Rs. 591 million and of 72 months (July 2008-June 2014) duration approved during February 2012.
  • Two years further extension anticipated till June 2016.