- Idea initiated during 2002-03 under PM package for Tharparker development.
- PC-1 Submitted during Dec. 2004.
- Project approved on 25th November 2006.
- Administrative Approval issued on 30th July 2008.
- Initial Location was at Jamshoro, shifted to SBA on 30th March 2009.
- Project Initial approved Cost Rs. 200.33 million
93.73 million Capital Cost
106.60 million Revenue Cost
- Completion Period 36 Months (Three Years) From July 2008 to June 2011.
- Revised PC-1 of Rs. 591 million and of 72 months (July 2008-June 2014) duration approved during February 2012.
- Two years further extension anticipated till June 2016.